Baltimore bridge collapse: Shipping to resume in weeks, back at full capacity by end of May

The main channel has been blocked since the Dali rammed into a support column of the Francis Scott Key Bridge on March 26. PHOTO: REUTERS

BALTIMORE - The US Army Corps of Engineers said on April 4 that it expects to open a new channel to the Port of Baltimore by the end of April, freeing up commercial shipping blocked by a collapsed bridge, and then restore port access to full capacity by the end of May.

The main channel has been blocked by wreckage since the Singapore-registered fully loaded container ship Dali lost power and rammed into a support column of the Francis Scott Key Bridge on March 26, killing six road workers and causing the highway bridge to tumble into the Patapsco River.

The Army Corps, part of a multi-agency team responding to the Baltimore disaster, announced the plans one day ahead of a visit by US President Joe Biden, saying that within four weeks the channel would be suitable for some roll-on roll-off vessels that transport automobiles and farm equipment.

The Port of Baltimore ranks first in the US for the volume it handles of automobiles and light trucks, and farm and construction machinery, according to the state of Maryland.

Most of that traffic has been suspended since the accident, though some terminal operations outside the affected area have resumed.

Earlier this week, two auxiliary channels suitable for emergency vessels, tugs and barges were opened on either side of the disabled ship, which is stuck beneath bridge debris with thousands of containers and a crew of 21 sailors still aboard.

But with depths limited to just over 3m and 4m, those two channels are too shallow for major cargo ships, which need a depth of 10.7m.

The corps said it expects to open a limited access channel over 85m wide and 10.7m deep, to the Port of Baltimore within the next four weeks – by the end of April.

By the end of May, it expects to restore port access to its full capacity with an over 213m-wide by 15m-deep navigation channel.

Before then, salvage crews must remove steel bridge debris from atop the Dali to extract it from the harbour, then clear the twisted metal and highway wreckage that fell into the water.

Ensconced within that debris are the bodies of four of the six highway workers who were killed.

The Biden administration has provided an initial US$60 million (S$80.9 million) in emergency funding to clear the channel and begin recovery, and Mr Biden said he would ask Congress to fund the complete rebuilding of the bridge. REUTERS

Remote video URL

Join ST's Telegram channel and get the latest breaking news delivered to you.